Requirements and establishment of the single allocation platform
Pursuant to Article 49(1) of the FCA Regulation, all TSOs need to develop a proposal for the requirements and establishment of the single allocation platform and submit it to the concerned regulatory authorities for approval and to the Agency for information.
Action 1: In April 2017, all TSOs submitted to all regulatory authorities and the Agency the proposal for the requirements and establishment of the single allocation platform.
Action 2: By December 2017, all regulatory authorities approved the proposal for the requirements and establishment of the single allocation platform.
The single allocation platform must be operational and comply with the functional requirements within twelve months of the approval of the proposal for the requirements and establishment of the single allocation platform by the last regulatory authority, i.e. by December 2018. The inclusion of the bidding zone borders with direct current interconnectors must be completed within the additional 12 months, i.e. by December 2019.
You can find documents related to the above actions here.
You can find the exact dates of the above actions in the implementation table here.
You can find the approved requirements and establishment of the single allocation platform here.
Sharing of costs of establishing, developing and operating the single allocation platform
Pursuant to Article 59 of the FCA Regulation, all TSOs need to develop a proposal for a methodology for sharing the costs of establishing, developing and operating the single allocation platform and submit it to the concerned regulatory authorities for approval and to the Agency for information.
Action 1: In April 2017, all TSOs submitted to all regulatory authorities and the Agency the proposal for the methodology for sharing the costs of establishing, developing and operating the single allocation platform (together with their proposal for the requirements and establishment of the single allocation platform).
Action 2: By December 2017, all regulatory authorities approved the proposal for the methodology for sharing the costs of establishing, developing and operating the single allocation platform.
The methodology for sharing the costs of establishing, developing and operating the single allocation platform should be implemented by twelve months after its approval by the last regulatory authority, i.e. by December 2019.
You can find documents related to the above actions here.
You can find the exact dates of the above actions in the implementation table here.
You can find the approved proposal for the methodology for sharing the costs of establishing, developing and operating the single allocation platform here.